2017-2018
First Step
2018-2020
Second step
2018-2022
Third Step
Этап реализации проекта 1
Construction of a closed two-level contour of dust-wind shields along the perimeter of the territory of the terminal terminal Astaf'eva
2018
Nov
Term for completion of the first stage
21.569
meters
Project area
250
Support structures

2 screen outlines

  • Internal circuit: dust-windproof mesh
  • External contour: metal panels 22 meters high (from the south, east and north of the terminal), from the side of the sea pier - 25 meters
75%
program implementation at the moment
80%
implementation of an active water-dust suppression system at the terminal
Этап реализации проекта 2
The erection of a hinged arch structure above the zone of the railway freight front of the terminal
9000
sq. m.
Total area
30
meters
Height of structure
2018
December
Design, coordination, expertise
2019
March
Start of construction
2020
November
Putting the object into operation
Этап реализации проекта 3
Joint tripartite international project on the construction of closed storage and reloading complexes
45
meters
height of the dome "in the skate"
6400
sq.m.
area of one warehouse
85T
handling capacity